Concrete Staircase and Ramp Details by Lai Chungyi is a document available to read on EtoBox.
1. The document provides a breakdown of the materials, labor, and time required to construct a staircase, steps, ramps, and finishes for the project. It includes formwork, reinforcement, concreting, and finishing works for the various elements. 2. A total duration of 8 days is estimated for the staircase formwork, 7 days for reinforcement, 5 days for concreting, and 6 days for finishes. For the steps, durations of 3, 2, and 7 days are given for formwork, reinforcement, and finishes respectively. 3. Constru