Samarang Project Phase I Dashboard by Manor Safeie is a document available to read on EtoBox.

The document provides a dashboard summary of the Samarang Project including its current progress, costs, schedules and key performance indicators for Phase I. As of December 2010, Phase I was 12.99% complete against a target of 14.73%, with actual costs of $13.3 million and no variance in its planned or expected finish dates of October 17, 2011. Several metrics like QHSE performance, manpower ratio and invoice ratio were also provided for Phase I.