The daily work programme outlines two tasks for road reconstruction from Kuril Flyover to Kanchon Bridge from October 3, 2020. Standard Penetration Tests will be conducted from 8:30 AM to 6 PM from chainage 5+000 to 3+750 by Saiful. Sub-Grade Bed Tests and level checks will take place from 4-6 PM at chainage 5+570 to 5+670 by Engineer Khorshed. The planning engineer prepared the work program which was approved by the project manager.