Can I read Project Earned Value Analysis Report on EtoBox?

Project Earned Value Analysis Report by mayur_lanjewar is a document available to read on EtoBox.

What is Project Earned Value Analysis Report about?

This document provides an activity-based earned value analysis for a construction project. It lists 22 activities with details on their planned value, earned value, actual cost, and estimates to complete. The total planned value is Rs. 13,864,015.70 while the total earned value is Rs. 13,848,719.70 and total actual cost is Rs. 13,795,753.14, resulting in a positive cost variance. Several activities have estimates to complete, with the largest being Rs. 375,318.80 for PCC work.