Man-Hours Calculation for Switchyard by erkamlakar2234 is a document available to read on EtoBox.

The document contains a work breakdown structure and schedule for a 132kV plant end switchyard project. It includes 18 items in section A related to design drawings and calculations. Section B contains 12 technical vetting items for switchyard equipment. The schedule outlines the number of days, hours, and estimated manhours for 3 engineers to complete the work across 3 bays, with a total estimated manhour of 1,776 hours.