Daily Civil Engineering Progress Report by jk.venkatesh is a document available to read on EtoBox.
The daily construction report summarizes work done on December 12, 2022 for the construction of a high speed railway involving viaducts, bridges, and tunnels between Maharashtra and Gujarat in India. On this day, formwork was in progress for well foundation P17, beam erection was underway at P19, deshuttering was taking place at well foundation P12, and air jetting was in progress at well foundation P13. A sacrificial slab was also cast at well P11. The report notes a crane breakdown and extinguisher issue