JCT Delay Notification and Time Extensions by LG is a document available to read on EtoBox.
What is JCT Delay Notification and Time Extensions about?
The Contractor must notify the Architect/Contract Administrator in writing of any delay to the works or likely delay at the earliest opportunity. The notice must state the cause of the delay. It should also provide an estimate of the delay to completion if possible. Failure to provide proper notice could result in the Contractor not receiving a full extension of time or being liable for delays. The Architect/Contract Administrator will assess if completion is delayed and if the cause is a relevant event lis