Can I read Delay Analysis for Barabanki-Malhaur Project on EtoBox?
Delay Analysis for Barabanki-Malhaur Project by replanningrvnl is a document available to read on EtoBox.
What is Delay Analysis for Barabanki-Malhaur Project about?
The document outlines the delay analysis for the Barabanki-Malhaur 3rd & 4th Line Project as of January 31, 2025, detailing various delay events, their causes, and effective delay days associated with each event. Key issues include delays in providing Right of Way, approvals for designs, and obtaining necessary clearances, leading to significant project delays totaling 526 days in some cases. The analysis emphasizes the impact of external factors like forest clearance and logistical challenges on project ti