PT Merdeka Copper Gold Progress Report by rony 2222 is a document available to read on EtoBox.
What is PT Merdeka Copper Gold Progress Report about?
This weekly progress report provides updates on the Tujuh Bukit Oxide – HLP Pad C Stage 1 ongoing project. As of April 17th, cut works were at 406k m3 of the 690k m3 plan (58% complete), fill works were at 277k m3 of the 813k m3 plan (34% complete), and underdrainage works were at 1619 m of the 3750 m plan (43% complete). The project