Dalampasigan Company began construction of a new citrus processing plant on January 2, 2020, which was completed on September 30, 2021. Construction expenditures totaled P2,400,000 over the period. Dalampasigan also took out a P1,100,000 construction loan at 12% interest and had P4,000,000 in outstanding 9% bonds during 2020 and 2021 to fund construction.