Weekly Report: Mombasa Port Construction by michael is a document available to read on EtoBox.
Mwonga Michael Mwendwa submitted his weekly report as a graduate trainee for the Mombasa Port - Area Development Project Package 3 construction of the Mteza - Kibundani section. Over the week he worked on reinforcement steel and concrete quantities for three box culverts along the section at Km 14+430, Km 15+170, and Km 16+860. He also inspected reinforcements, formwork, and concreting work at Km 15+170.