Can I read Water Project Progress Report 2018 on EtoBox?
Water Project Progress Report 2018 by thisula is a document available to read on EtoBox.
What is Water Project Progress Report 2018 about?
This document provides an update on the planned and actual progress of various components of a water project as of December 2018. The raw water intake and pumping station was planned to be 79.49% completed but was only 66% finished. The water treatment plant was planned at 40.77% but reached 39.68%. Tower sites and ground reservoirs planned 58.85% but only achieved 43.8% while pipe laying and transmission were ahead of plan at 51.54% and 43.68% respectively.
- Author
- thisula
- Language
- EN