Daily Tiling Progress Report: 4-24-25 by 2021-200781 is a document available to read on EtoBox.
The Daily Accomplishment Report for April 24, 2025, details the completion of tiling works in 17F Unit E and 20F Unit E,P, with ongoing work in the 20F hallway. A manpower assignment lists various positions and their respective floors, including technicians and laborers. The contractor for this project is Acemack, and the client is MEC.