Permit Application Timeline and Delays by ewanz89 is a document available to read on EtoBox.
What is Permit Application Timeline and Delays about?
The document outlines the scheduled, actual, and recommended timelines for a construction permit application and work commencement process. The initial permit application was submitted on February 15, 2013 but the work did not commence until May 30, 2013 due to a 34 day delay in permit processing. Multiple issues such as rejected applications and requests for changes caused further delays, with work finally ending on December 19, 2013, over 10 months after the original scheduled commencement date.