Progress Report: RSU Bunda Padang Construction by Satria SE is a document available to read on EtoBox.

The daily activity report for the construction of the new RSU Bunda Padang indicates a cumulative progress of 1.38% with a remaining target of 10.69%. Key activities include the completion of concrete pouring at points 4B and 4C, and the ongoing demolition of the kitchen corridor. There are site issues, such as unrelocated pipe installations, and a total of 21 workers were present on site today.