The DolWin 4 and BorWin 4 HVDC grid connection projects, located in the German sector of the North Sea, are being developed by Dragados Offshore in consortium with Siemens Energy, with completion dates set for November 2028 and February 2029 respectively. Each project will feature a 900 megawatt capacity system for electrical energy transmission, with a total transmission capacity of 1.8 GW sufficient to supply a city like Hamburg. The projects include offshore platforms and onshore substations connected to