Downtown Arena Project Update Report by Emily Mertz is a document available to read on EtoBox.
The report recommends proceeding with design development of the downtown arena based on the $450 million schematic design and budget. Public engagement on the schematic design was positive overall. Cost estimates for the arena and related infrastructure total $485 million, exceeding the budget. Additional cost saving measures are being pursued to reduce costs by $38.9 million and achieve the $450 million budget.