Can I read Progress Report: Conveying System Project on EtoBox?
Progress Report: Conveying System Project by adityadh is a document available to read on EtoBox.
What is Progress Report: Conveying System Project about?
The document provides a progress calculation report for a conveying system project in PT Petrokimia Gresik from February 1-7, 2013. Engineering progress was 24.75%, procurement was at 8.21%, and construction was at 0.095%. Overall progress for the project was 6.84%, ahead of plan by 1.86%. A project S-curve is also shown plotting planned vs actual progress through August 2013.
- Author
- adityadh
- Language
- EN