Technical Justification for Piling Design by Dito Narendra is a document available to read on EtoBox.
The document provides a technical justification for using three rows of piles between grid lines 11 and 12 for the intake structure of the Muara Tawar Combined Cycle Power Plant Block 2, 3, and 4 Add-On Project. Calculations show that using two rows of piles is insufficient and results in many piles being unsafe under load. Using three rows of piles satisfies the design requirements, with the piles being loaded near their full capacities but still safe. The three row configuration is needed for earth retent