Can I read Basic Construction Project Timeline on EtoBox?
Basic Construction Project Timeline by Erwin Obenza is a document available to read on EtoBox.
What is Basic Construction Project Timeline about?
This document outlines the basic construction plan for a substation project over 70 days from July 9 to September 17. It is divided into 3 main sections: establishment over 8 days, earthworks and substructure over 27 days, and superstructure over 39 days. Each section contains multiple activities with assigned subcontractors and estimated durations to be completed sequentially.
- Author
- Erwin Obenza
- Language
- EN