Davis Company uses job-order costing. They have a budgeted 65,000 direct labor hours, 9,000 machine hours, $350,000 in overhead, and $110,500 in direct materials. Their direct labor costs so far are $70,000. If overhead is applied based on direct labor hours, the rate would be $5 per hour (rounded to the nearest whole dollar). If overhead is applied at 135% of direct labor costs, the total cost of Job #504 would be $275,000 (rounded to the nearest whole dollar).