What is MRP: Scheduling for Dependent Demand about?
Here are the planned order receipts and releases based on the information provided: Week 1: A (planned order receipt): 30 Week 3: B (planned order release): 10 Week 4: A (planned order receipt): 30 The net requirements for A in week 5 is 50 units. With only 20 units projected to be available, an additional 30 units need to be received. Based on the 2 week lead time for A, orders need to be placed in weeks 1 and 4. 10 Bs are available to explode to make 20 As, so the remaining 30 As need to be