Optimizing Manufacturing Flow and Capacity by Mohamed El Naggar is a document available to read on EtoBox.

HPI will produce all 3,000 units of its more profitable product, HPI-2, using 1,500 hours of the 2,400 hour production capacity. The remaining 900 hours will be used to produce 900 units of HPI-3. To maximize production through the constraint, the production process should be simplified, product design improved, setup reduced and other delays eliminated. Takt time, the rate of production needed to meet demand, is used to balance product flow through processes. For example, if 400 minutes per day are availab