Can I read Cost Variance Analysis for Project on EtoBox?
Cost Variance Analysis for Project by Tamara Clement is a document available to read on EtoBox.
What is Cost Variance Analysis for Project about?
The project is two months in and is behind schedule and over budget. The cost variance is -$5000, schedule variance is -$3000, CPI is 0.8, and SPI is 0.87. Using these values, the estimated cost at completion is $150,000, $30,000 over the original budgeted amount. The estimated time to complete the project is 13.8 months, 1.8 months longer than originally planned.