Nutri Food Project WBS and Evaluation by Hà My Nguyễn is a document available to read on EtoBox.
What is Nutri Food Project WBS and Evaluation about?
Here are the key steps to update the schedule to finish 2 weeks earlier using fast tracking: 1. Overlap task G (duration 3 days) with tasks D (duration 8 days) and B (duration 4 days) by 2 weeks. 2. Task G will now start after 2 days of task A instead of after task D finishes. 3. Task B will now finish after 2 days instead of 4 days by allowing it to overlap with task G. 4. The critical path is now: Start → A → B → C → F → H → End 5. The new projected finish date is 22 - 2 = 20 days, which is 2 week