JNNSM Phase I Batch II Query Clarifications by JinalS is a document available to read on EtoBox.
What is JNNSM Phase I Batch II Query Clarifications about?
The document provides clarifications to queries raised about Phase I Batch II of Jawaharlal Nehru National Solar Mission (JNNSM). Key clarifications include: developers can change PV technology until financial closure; losses are limited to CERC guidelines; capacity is measured in AC output after accounting for losses; multiple projects can be submitted by a company up to 50MW total capacity. The document also clarifies tariff rates will be the CERC approved rates of Rs. 15.39/kWh for normal depreciatio