Can I read NH-7 Project Delays in Uttarakhand on EtoBox?
NH-7 Project Delays in Uttarakhand by Shivendra Kumar is a document available to read on EtoBox.
What is NH-7 Project Delays in Uttarakhand about?
This document discusses the construction and upgradation of an existing road from km 430 to 468 in Uttarakhand, India as part of the Chardham Paryojna project. The contractor, NKG Infrastructure Ltd., was appointed on May 23rd, 2018 with a scheduled completion date of November 20th, 2020. Various hindrances caused delays including only 74.2% land availability initially versus the required 90%, religious pilgrimages using the road, land disputes, pending forest clearances, and insufficient muck disposal area
- Author
- Shivendra Kumar
- Language
- EN