STAGE2 Progress Week9 by Abd Ghofur is a document available to read on EtoBox.
What is STAGE2 Progress Week9 about?
The document outlines the work progress for the One Floor House Building Project Stage 2 in Pandaan, East Java, for the week of September 15-20, 2025. The project is currently 93.05% complete, with detailed progress reported on various construction tasks including masonry, plastering, concrete work, and electrical installations. The total amount spent so far is 175,995,752.31 Rp.
- Author
- Abd Ghofur
- Language
- EN