Can I read Project Schedule Optimization with H-Piles on EtoBox?

Project Schedule Optimization with H-Piles by Biswajit das is a document available to read on EtoBox.

What is Project Schedule Optimization with H-Piles about?

The document discusses the redesign of foundations for a deep car dumper vault (CDV) in a bauxite mining project. Originally, the CDV foundation was designed as a partially compensated raft supported by sheet pile walls during excavation. However, excavation caused a slope failure and sheet pile movement. The foundation was then redesigned as bored piles socketed in bedrock, requiring two months and $600,000 for installation. Alternatively, available steel H-pile sections were utilized, shortening installat