Resiting and M&E Project Timeline by Assem Elhajj is a document available to read on EtoBox.

What is Resiting and M&E Project Timeline about?

Civil work for substation 1 is scheduled to start in March and be completed by May, with the existing DG room to be demolished and site development nearby to be completed. Consultants are to submit shape drawings by February 14th and excavation can begin next week when civil construction drawings become available. The vendor for equipment supply is to be finalized by end of February and will be on board in April to deliver equipment by June after the purchase order is released and post order activities prog