Façade Cladding Progress Report by swami22 is a document available to read on EtoBox.

The document is a daily report summarizing the status of facade work for different areas as of March 17, 2011. It outlines the balance and progress of glazing, ACP cladding, and stone cladding work for areas A3, A2, B3, and the courtyard. Some tasks like canopy work and logo installation are on hold pending details, while other areas need clarification on stone cladding details from the architect. Grid removal is in progress to allow for concrete work.