Rourkela Steel Plant Battery No. 7 Feasibility by ACE CONSULTANTS is a document available to read on EtoBox.
The feasibility report proposes installing Coke Oven Battery No. 7 at Rourkela Steel Plant to ensure sufficient coke supply for Blast Furnace No. 5. The proposed battery will have a coal carbonization capacity of 1.0 Mtpa and use stamp charging technology. It will be located next to existing Battery No. 6 as a replacement during its planned rebuilding from 2024-25. The project cost is estimated at Rs. 2,317.64 crores and will be executed on a turnkey basis over 42 months. It is considered technically viable