Can I read Sewerage Work Progress Update 2007 on EtoBox?
Sewerage Work Progress Update 2007 by Suhaidi Alias is a document available to read on EtoBox.
What is Sewerage Work Progress Update 2007 about?
A progress update on sewerage work as of November 28, 2007 indicates that the total planned length of sewerage pipes is 1,774 meters, of which 885 meters had been completed as of November 7, leaving 889 meters remaining. The sewerage work started on September 1, 2007 and was planned to be completed by January 30, 2008, representing a duration of 188 days excluding holidays. As of November 28, the work was 65 days from the target completion date, with a daily target progress of 10.29 meters and actual progre