Darail and Tangir Project Progress Report by Asad Zahid is a document available to read on EtoBox.
The progress report for the AKL SCO project details the status of the Tangir and Darail sections, with Tangir having 255 poles installed and 25 remaining, while Darail has 188 installed and 182 remaining. A total of 1800 bags of cement have been received, with various contractors responsible for transportation to the respective sections. Alignment issues in the Darail section remain unresolved, but no additional poles are required for either section.