PH#5 Restoration Project Timeline by anurag srivastava is a document available to read on EtoBox.

The document is a Gantt chart that outlines the timeline and status of tasks for restoring PH#5 at Ester Industries Limited from October 2020 to January 2021. Key tasks included dismantling the existing structure, erecting a new structure, installing conveyor belts and pipelines. As of mid-December 2020, several tasks were still underway such as column strengthening, valve replacement, and material installation. The project was 90% completed as of early December with an expected end date of January 31, 2021