Here are the steps to solve this problem: A) Build the AOA PERT: A (4) → D (6) B (7) → E (3) → F (11) C (5) B) The preferable length is 13 days to avoid penalties. To achieve this, activities A, B and C must be crashed. C) The total cost is: Normal cost of A, B, C = 1000 + 2000 + 1200 = 4200 Crash cost of A = 500 * 1 day = 500 Crash cost of B = 500 * 3 days = 1500 Crash cost of C = 300 * 1 day = 300 Total