Change of Scope in EPC Agreement by RAJSHREE MAURYA is a document available to read on EtoBox.
This document outlines procedures for changes in the scope of work (called "Change of Scope") on an infrastructure project. 1) The Authority may require modifications to the works within 6 months of the start date. The Contractor must submit a proposal for any associated costs or cost savings within 15 days. 2) Additional changes may be required up to 50% of the original scheduled construction period, but these cannot result in extension or prolongation claims against the Authority. 3) Payment for app