Can I read Malong-A Platform Rig Entry Preparation on EtoBox?
Malong-A Platform Rig Entry Preparation by mohd nizam kamarulzaman is a document available to read on EtoBox.
What is Malong-A Platform Rig Entry Preparation about?
The document outlines a detailed schedule for the provision of surface preparation work and rig entry for the Malong-A platform, spanning a total duration of 14 days. It includes tasks such as equipment and manpower mobilization, crane boom repositioning, removal of the crane boom rest, and ensuring safety measures at the cellar deck area. Each task is broken down with specific durations and prerequisites to ensure a systematic approach to the project.
- Author
- mohd nizam kamarulzaman
- Language
- EN