Subcontract for Pipe Sanding and Painting by ScribdTranslations is a document available to read on EtoBox.

This contract establishes the terms for the Subcontractor to carry out sanding and repainting of tubes as part of the construction of a coliseum in Huaraz. The Subcontractor agreed to complete the work in 5 days in exchange for S/1400. The Contractor is responsible for payment once the services are approved by the resident engineer. Both parties agreed on procedures to resolve disputes and terminate the contract early.

Author
ScribdTranslations
Language
EN