Can I read Sarawak Tatau Road Project Progress Report on EtoBox?

Sarawak Tatau Road Project Progress Report by Premier Toh is a document available to read on EtoBox.

What is Sarawak Tatau Road Project Progress Report about?

The monthly progress report for the construction of the new road from Tatau to Kuala Tatau, as of November 25, 2022, indicates that the project is experiencing delays, with a cumulative physical progress of 83.44% against a planned schedule of 100%. Various extensions of time (EOT) have been approved due to factors such as force majeure and design changes, resulting in a revised completion date. Financially, the project has incurred total expenditures of RM 17,102,804.23, with actual cumulative financial pr