The document provides a construction programme for the Moxy Hotel in Manchester with 140 bedrooms. Key dates include: - Site establishment from December 9th 2019 to January 10th 2020. - Demolition and enabling works from January 6th 2020 to March 27th 2020. - A 4 week COVID-19 closure from March 30th 2020 to April 24th 2020. - A 2 week suspension of works from April 27th 2020 to May 8th 2020. - The construction period runs from May 11th 2020 to the planned completion date of August 30th 2021.