Submittal Status for Civil Drawings by Mary Baino is a document available to read on EtoBox.

The document provides a status report for shop drawings for the Margalla Building project. It shows that 407 total drawings were submitted, with 156 being approved, 99 approved with comments, and 77 pending approval. It also lists 13 individual civil drawings, showing submission dates and responses. The approval time for drawings was 15 days on average.