LAVIE YARD PROJECT Daily Report by Walid Elsaid is a document available to read on EtoBox.

The LAVIE YARD PROJECT is set to run from February 2, 2025, to February 1, 2027, with 665 days remaining. Current site activities include formwork, backfilling, and concrete curing across various locations, while the site is staffed with 42 technical personnel and 237 workers. The weather is sunny with a temperature of 30°C and wind speed of 15 KM/HR.