SUKE Elevated Expressway Daily Report by KumaResan Subramaniam is a document available to read on EtoBox.

What is SUKE Elevated Expressway Daily Report about?

1) Daily report from Acre Works Sdn Bhd for construction work on March 22nd, 2019 for the Sungai Besi – Ulu Kelang Elevated Expressway (SUKE) Package CA1 project. 2) Construction activities on Section 2 included casting a pile, preboring another pile, installing forms and scaffolding for a pilecap, and continuing rebar installation for another pilecap. Rock was encountered while sinking a piling. 3) 14 general workers, 1 site supervisor, and machinery including 2 crawler cranes, 1 mobile crane, 3 excavat