Here are the steps to solve this problem: 1. Draw the network diagram and link the activities based on their dependencies 2. Calculate the earliest and latest start/finish times using forward and backward pass 3. Identify the critical path - activities with zero total float 4. Calculate the buffer times (CBT and BT) The critical path is activities 1, 2, 4, 8 with a total duration of 36 hours. The non-critical activities are 3, 5, 6, 7 with buffer times available.