Monthly Report EPC PLTM Cileunca by annisa is a document available to read on EtoBox.
This report provides a monthly progress update for the construction of the 2 x 500 kW Cileunca PLTM project in Indonesia. Based on the data provided, general works like site preparation and temporary facilities are over 75% complete. Civil works like access road construction and penstock pipe installation are approximately 25-65% finished. The overall local construction progress to date is reported as 22.86% complete, compared to the total EPC contract progress of 13.11%.