The document provides a work breakdown structure and schedule for constructing a 2-storey residential house. It includes 63 activities related to site work, fabrication of steel reinforcement, foundation, walls, beams, slabs, columns, roof, and finishing work. For each activity it specifies predecessors, duration, optimistic and pessimistic time estimates, and variance. The total projected duration is 258 days with a variance of 13.39 days and standard deviation of 3.73 days. The scheduled completion date i