Weekly Progress Report - Balrampur by Sandeep Singh is a document available to read on EtoBox.
What is Weekly Progress Report - Balrampur about?
Weekly progress report for Balrampur shows a weekly asking rate of 570 units and current rate of 188 units, leaving a gap of 383 units. The planned completion date is August 15th but current progress means the expected completion date will be November 5th, resulting in an 83 day delay in completion. Erection completion increased from 270 to 375 units between the first and second weeks of July but other key metrics like legalization submissions and approvals all remained at 0.