Can I read FSD-3026-25 + (F) + FESCO + Delay in Upgradation of Transformer 3-Phase 100 KVA on EtoBox?
FSD-3026-25 + (F) + FESCO + Delay in Upgradation of Transformer 3-Phase 100 KVA by edyanky is a document available to read on EtoBox.
What is FSD-3026-25 + (F) + FESCO + Delay in Upgradation of Transformer 3-Phase 100 KVA about?
The complaint filed by Mr. Asrar Ahmad against Faisalabad Electric Supply Company (FESCO) concerns the alleged delay in upgrading a transformer to meet the increased power needs of his locality. The investigation revealed that FESCO failed to provide adequate voltage, constituting maladministration, and recommended the installation of a 200 KVA transformer. The agency is required to submit an implementation report within 45 days, with options for the aggrieved party to file a review or representation within