This daily site record provides an update on construction progress at Hougang Town. 13 of 27 lower deck pile caps have been completed so far (48.15% complete). 28 of 30 upper deck pile caps are finished (93.33% complete). Other structural works like MSCP piles, contiguous bored piles, and grout piles are 100% complete. Detention drain construction is now at 62.66% complete. Formwork is being installed to cast the top slab and detention drain wall on Saturday and Friday respectively.